64

Interdependent projects coordinated across five program towers

600k

Advanced smart meters deployed as part of the modernization

61

Substations modernized, supported by approximately 340 miles of fiber infrastructure

Modernizing Smart Grid & Smart Meter Delivery Through Integrated PMO Leadership

A major regulated electric and gas utility launched a large, multi-year Smart Grid and Smart Meter modernization involving dozens of interdependent projects across metering, grid technology, distribution automation, and substation infrastructure. Greencastle established and led the central Program Management Office, providing the governance, project controls, reporting, and coordination needed to manage the program as one integrated portfolio. Through standardized delivery methods, executive dashboards, master scheduling, risk management, and regulatory traceability, the PMO improved accountability across program teams and supported the successful deployment of new metering and grid capabilities on a regulator-driven timeline.

THE SOLUTION

Greencastle created an integrated PMO operating model that combined program governance, project controls, risk management, change enablement, and regulatory compliance.

Benefits

  • Centralized Program Coordination
    Unified 64 interdependent projects across five program towers through executive dashboards, portfolio governance, master scheduling, and structured cross-project coordination.
  • Improved Delivery Visibility
    Provided leadership with timely insight into project status, dependencies, risks, and release readiness, supporting more informed go/no-go decisions.
  • Audit-Ready Program Execution
    Established requirements traceability, risk registers, and regulatory reporting controls that supported accountability throughout the program and helped maintain alignment with federal and state obligations.
APPROACH

PMO Assessment & Stand-Up
Greencastle assessed existing delivery tools, reporting requirements, and project-management practices to identify gaps between the current and desired operating models. The team established a formal PMO charter, created a centralized knowledge-management structure, and introduced standardized methods, tools, training, and coaching.

Integrated Program Controls
Greencastle built the program’s operating rhythm through executive dashboards, status reporting, portfolio governance, and an integrated master schedule. A synchronization matrix helped identify conflicts and dependencies across projects, while requirements traceability connected legal and program obligations to release planning and executive decision-making.

Adoption, Risk & Operational Transition
Using a phased adoption model, Greencastle led risk and issue management, organizational change, and transition-to-operations planning. The team established accountable risk registers, prepared stakeholders for new processes and technologies, and supported the creation of an integrated cybersecurity function aligned with federal guidance.

CONCLUSION

Greencastle brought structure, accountability, and delivery discipline to one of the utility’s largest capital modernization programs. By establishing a people- and process-focused PMO, the team coordinated interdependent initiatives, improved executive visibility, strengthened risk and regulatory controls, and supported the transition of new grid capabilities into operations. The program delivered approximately 600,000 smart meters, modernized 61 substations, and reached substantial completion on its regulator-driven timeline. The resulting governance and project-control framework gave both executives and regulators greater confidence in program execution and reporting.

Check Out the Full Case Study